Geotechnical Site Investigation, Slope Stability/Soil Settlement Analysis and Material Testing were done.
Project Goal
The purpose of the site investigation was to address the following:
Ground surface elevation at each borehole location Obtaining soil samples at 0.75 m interval. Conduct soil shear strength parameters and impact on subgrade performance.
Identification of utility crossings and any other pertinent information for the City of Edmonton.
Results
A total of 3 boreholes was drilled during the drilling program.
ZALIG installed inclinometers and monitored it for deep seated movements. Surficl movement was monitored using monuments and 6 by 6 grid to determine any potential movement.